City Hall · November 17, 2026
Council moves ahead on data centre rules, with bylaw options due by March 2027
Calgary city council directed staff to prepare land-use changes that could allow a moratorium on large data centres and to study their effects on water, power and noise.

Key facts
- Council directs staff to prepare bylaw options, including possible moratorium powers
- Bylaw report due by March 2027; impact research due in Q4 2027
- Study to cover water, electricity and noise
- Provincial guidance applies to data centres of 75 MW or more
Calgary city council has agreed to move forward with work on rules for large-scale data centres, following a committee recommendation earlier this month that came in response to a large data centre land-use application in the city's far northeast [1].
Council directed city administration to prepare options for changes to the Land Use Bylaw that could allow a moratorium on development applications for new and emerging sectors [1]. Administration was also told to bring back possible bylaw amendments to govern the buildings themselves, and to research how large data centres affect water, electricity and noise [1]. The report did not give a vote count [1].
Administration is expected to report back on the bylaw changes, including moratorium powers and any data-centre-specific updates, by March 2027 [1]. The research on impacts is expected in the fourth quarter of 2027 [1].
Ward 2 Coun. Jennifer Wyness, who led the push for data centre guidelines, said the city's bylaws have a gap because they do not specifically provide for a moratorium, and noted that other Alberta municipalities have adopted one [1]. She also raised concern that, according to administration, there is industrial land already inside city limits where a data centre would not need a land-use change [1]. Administration said its development permit process is robust enough to identify concerns [1].
Ward 13 Coun. Dan McLean said he wants strong safeguards around construction, while Ward 14 Coun. Landon Johnston said he wants the facts right and no bias toward a particular outcome [1]. Mayor Jeromy Farkas said the city has a vacuum when it comes to mega-scale data centres and called for strict rules on noise, water and electricity [1].
Provincial guidance covers data centres of 75 megawatts or more and gives priority to projects that generate their own power [1]. The Alberta Utilities Commission recently rejected a power generation site for a proposed data centre near Olds [1].
Each statement is marked with the source it comes from. This story summarises those reports in its own words and adds no opinion.
Sources
This story is written from the reporting and official notices below. Read them for the full details.
- Calgary forges ahead with research, land-use amendments for large-scale data centres LiveWire Calgary, November 17, 2026
Topics: City Council, Development, Technology, Energy, Water