Executive committee endorsed studying curbside bus-only lanes for the Max Green route and $16.6 million in Green Line extension planning; council still has to decide.

Key facts
- Curbside Max Green bus lanes estimated at $511 million; full transitway about $2.1 billion
- $16.6 million requested to plan Green Line extensions
- Green Line phase one expected to open by 2031
- Full council still has to decide
City council's executive committee on Tuesday, Nov. 3, endorsed a push for faster improvements to the Max Green bus rapid transit route on Centre Street, after a city report put the cost of fully building it at no less than $511 million [1][2][3].
The report set out four scenarios. The lowest-cost one, about $511 million, would add curbside bus-only lanes from downtown to Keystone Hills, more Max stops, new terminals at 96 Avenue and 144 Avenue N., and a bus station in Crescent Heights. The most expensive, a fully separated transitway down the middle of Centre Street along the future Green Line alignment, is estimated at about $2.1 billion [1][3].
The report followed an amendment by Ward 3 Coun. Andrew Yule when council approved a revised downtown Green Line route in September [3]. Yule's motion, endorsed by committee, asks staff to report by mid-2027 on how curbside lanes would affect businesses, parking and loading, and on possible funding from other governments [2][3]. The Calgary Herald reported the committee vote as 9-2, with councillors Andre Chabot and Mike Jamieson opposed [3]. No money for the bus lanes has been approved, and the recommendation still needs a decision by full council [1][2].
Yule and Ward 4 Coun. DJ Kelly said the north leg of the Green Line LRT is unaffordable for now. Kelly cited high-level estimates of about $3 billion for a southeast extension to Seton and $4 billion for LRT north [1]. Yule said about 30,000 people use the Centre Street corridor each day [1][3]. "I need service now," Yule said [3].
Sarah Huber, the City's director of project development, said some bus lane work, such as land purchases and utility relocation, would still help an eventual Green Line [1]. Mayor Jeromy Farkas said he preferred an option that could later be converted to LRT [1].
Separately, administration said it will ask for $16.6 million in the coming four-year budget to plan the Green Line's extensions: $4.1 million for the southeast leg from Shepard to Seton and about $12.4 million to $12.5 million for the north leg from downtown to 160 Avenue N. Global News and the Herald give slightly different figures for the north leg [2][3]. Huber said this is planning and preliminary design, not construction [3]. Council will decide on that funding during budget deliberations later this month [2].
The first phase of the Green Line, from Shepard to 10 Avenue S. in the Beltline, is under construction with a budget of about $6.2 billion to $6.25 billion and is expected to open by 2031 [2][3].
Each statement is marked with the source it comes from. This story summarises those reports in its own words and adds no opinion.
High-level cost estimates for north and southeast transit options
| Estimate ($B) | |
|---|---|
| Max Green curbside bus lanes | 0.511 |
| Centre Street transitway | 2.1 |
| Green Line Shepard to Seton | 3 |
| Green Line Eau Claire to 40 Ave. N. | 4 |
| Green Line phase one (budget) | 6.25 |
Source: Calgary Herald (via Yahoo News Canada)
Sources
This story is written from the reporting and official notices below. Read them for the full details.
- 'Dead' Green Line LRT north prompts push for expediency on Max Green BRT LiveWire Calgary, November 3, 2026
- Green Line LRT extension study proposed, north Calgary councillors seek bus service improvements Global News, November 4, 2026
- Councillors propose $511-million for dedicated bus lanes up Centre Street Calgary Herald (via Yahoo News Canada), November 3, 2026
The places in this story
Figures for each, from public data: Ward 3 · Ward 4 · Crescent Heights · Keystone Hills · Seton
Topics: Transit, City Council, Budget and taxes, Roads and traffic
← Newer: Provincial inspection of Bearspaw feeder main finds long-standing weaknesses at the City
Older: Fifth Safer Calgary operation leads to 10 people charged and 170 warrants executed →